Construction Updates
Nashua - Merrimack - Bedford 13761
Project 13761A
F. E. Everett Turnpike (FEET) NB and SB between 8 (Somerset Parkway) and Exit 10 (Industrial Drive)
This project will widen the Turnpike from two to three lanes in each direction. The construction work includes pavement widening and reconstruction, replacement of the bridges over Pennichuck Brook, median rehabilitation, overhead sign structure replacements, inclusion of ITS infrastructure, construction of stormwater quality treatment facilities, and the removal of the tunnel located under the FEET at Exit 10. Project completion is scheduled for May 2028.
Recent Activities (as of early November 2026)
Southbound
- Excavation for new roadway has been completed south of the bridge.
- Underdrain installation has started south of the bridge.
- Excavation for ditches and side slopes has started north of the bridge.
Northbound
- No recent activity.
Exit 10
- No recent activity.
Pennichuck Brook Bridge
- Pavement has been removed from the old southbound bridge.
Upcoming Work (November 2026 to December 2026)
Southbound
- Drainage and earthwork will continue on the proposed southbound roadway.
Northbound
- Minor activity expected.
Exit 10
- Minor stockpile management along the southbound ramp.
Pennichuck Brook Bridge
- Bridge demolition will begin.
General Traffic Implications
Fall 2026
- Rolling roadblocks, shoulder closures and night work, as needed, for temporary roadwork, as traffic allows.
- Rolling roadblocks and short-term ramp closures will be required to shift traffic to Phase 4 TCP.