Project Schedule
Nashua - Merrimack - Bedford 13761
Construction Schedule & Project Breakouts (PDF)
2016 - 2018
- Public Officials Meetings
- Develop design alternatives
- Research environmental resources
2018
- Hold Public Informational Meetings
- Evaluate design alternatives
- Evaluate environmental impacts (wetlands, water quality, noise, etc.)
- Publish Environmental Study
- Public Hearing
2019 - 2033
- Final Design
- Right-of-way acquisitions and easements
- Environmental permitting
- Construction
2022
- Start of construction for the 13761D Project (F.E.E.T. widening of the 2-lane section north of Exit 13 in Merrimack to north of the I-293 diverge in Bedford)
2023
- Start of construction for the 13761E Project (F.E.E.T. widening of the 2-lane section north of Exit 12 to south of Exit 13 in Merrimack)
2024
- Start of construction for the 13761A Project (F.E.E.T. widening of the 2-lane section north of Exit 8 in Nashua to south of Exit 10 in Merrimack)
2026
- Start of construction for the 13761B Project, Bridge Replacements (Baboosic Lake Road and Wire Road bridges in Merrimack)
2027
- Anticipated start of construction for the 13761C Project (F.E.E.T. widening of the 2-lane section north of Exit 11 to north of Souhegan River bridge in Merrimack)
2030
-
Anticipated start of construction for the 13761G Project
(F.E.E.T. widening of the 2-lane section north of the Souhegan River bridge to north of Exit 12 in Merrimack)
- 13761G Project location map (PDF)
- 13761G Project plan view (coming soon)