Project 13761E

Turnpike Widening from Exit 12 (Bedford Road) to the Bedford Toll Plaza

Recent Activities (as of early April 2025)

Northbound

  • Placed humus around sign structure foundations.

Southbound

  • Placed humus around sign structure foundations.
  • Began installing chain link fence around BMP 1188.
  • Began installing right-of-way fence.

Upcoming Work (April 2025 to May 2025)

Northbound

  • Install right-of-way fence, signs, and guardrail.

Southbound

  • Continue installing right-of-way fence.
  • Install signs and guardrail.
  • Finish grading berm near STA 1179 +/-.

General Traffic Implications

Spring 2025

  • Rolling roadblocks and shoulder closures, as needed, for temporary roadwork, as traffic allows.